The grid just had a very Washington week.
Big Tech is heading to the White House to pledge ratepayer protection. The Department of Energy finalized the largest power-sector loan in U.S. history. Wholesale and capacity prices are climbing across major markets. And a former Tesla executive just raised $140 million to rebuild one of the grid’s most boring — and most critical — components.
Demand is here. Capital is moving. Prices are signaling stress.
Major Stories
AI & DATA CENTERS
White House Hosts Big Tech for “Ratepayer Protection” Pledge
The White House will host major hyperscalers (including Microsoft, Amazon, Google, and Meta) as part of a push to formalize a voluntary pledge aimed at insulating residential customers from AI-driven electricity cost increases.
The emerging framework encourages data centers to secure dedicated supply, invest in new generation, and avoid shifting infrastructure costs onto household ratepayers. It reflects growing bipartisan political sensitivity around rising electricity bills and the optics of hyperscale growth.
The move follows a string of state-level fights over large-load cost allocation and comes as capacity prices and transmission expansion costs rise in multiple regions.
Why It Matters - Data center electricity demand has moved from engineering conversation to political liability. The White House stepping in signals that large-load governance is becoming federalized.
Grid Take - When voluntary pledges start getting negotiated in Washington, regulation is usually not far behind. The industry has a narrow window to shape its own rules before Congress does it for them.
FEDERAL FINANCE
DOE Finalizes Largest-Ever Power Loan

The Department of Energy finalized a $26.5 billion loan package to support Georgia Power and Alabama Power infrastructure expansion. It’ll be the largest energy-sector loan ever issued by the federal government.
The funding supports new gas generation, nuclear investments, transmission expansion, storage, and broader grid modernization. It’s all tied to load growth across the Southeast, including AI and industrial expansion.
The message is unmistakable: Washington is willing to underwrite large-scale grid expansion when demand signals are strong enough.
Why It Matters - This isn’t grant funding. It’s leverage. A loan package of this size reshapes capital timelines and reduces financing risk for large, multi-year infrastructure builds.
Grid Take - Industrial policy is no longer theoretical. It’s being capitalized at scale. The question is whether public leverage accelerates supply fast enough to blunt price pressure.
MARKETS
Wholesale and Capacity Prices Keep Climbing
Wholesale power and forward capacity prices continue rising across several U.S. markets, most notably in PJM, where recent capacity auctions cleared at historically elevated levels, with prices in some zones exceeding $200 per megawatt-day. That represents a sharp increase from prior auctions and reflects tightening reserve margins as demand forecasts rise.
The drivers are not mysterious. Load growth from data centers and broader electrification is arriving faster than new firm generation can be permitted and built. At the same time, transmission constraints are limiting the movement of power across regions, and thermal retirements continue to outpace dispatchable replacements in several markets. The result is visible in utility earnings calls and regulatory filings: higher forward procurement costs, more aggressive capital plans, and mounting political pressure as wholesale price signals begin filtering toward retail bills.
Why It Matters - Capacity markets are the quiet stress gauge of the grid. When prices surge, they’re signaling tight supply relative to expected demand.
Grid Take - Price signals are not a failure. They’re a warning. The risk isn’t high prices … it’s ignoring them while slowing the build cycle.
INFRASTRUCTURE
Heron Power Raises $140M for Solid-State Transformers

Heron Power, founded by former Tesla executive Drew Baglino, raised $140 million to build a factory producing solid-state transformers designed to improve electricity transfer from renewable generation to the grid. The timing is not accidental. Lead times for large power transformers in the U.S. have stretched to 18 to 36 months, with utilities reporting multi-year delays for certain high-voltage units as transmission buildouts accelerate and global supply chains tighten.
Unlike traditional transformers, solid-state units are smaller, lighter, and digitally controllable, allowing faster voltage regulation and integration of variable renewable output. Heron plans for a facility capable of producing 40 gigawatts of transformer capacity annually, a meaningful figure in a country where total peak demand is roughly 740 gigawatts. If achieved, that output would represent hardware throughput equivalent to roughly five percent of U.S. peak load each year, targeting one of the least glamorous but most binding constraints in grid expansion.
Transformer shortages have quietly become a bottleneck for new transmission lines, renewable interconnections, and even routine grid upgrades. This is a bet that the growth story in power isn’t just turbines and data centers, but the steel and silicon that let electrons actually move.
Why It Matters - Grid expansion isn’t just about turbines and wires. It’s about components. Transformers are a hidden choke point in scaling transmission and distributed generation.
Grid Take - The grid’s weakest link is often the least glamorous one. If hardware bottlenecks persist, capital will chase the constraint.
CORPORATE PROCUREMENT
Google Expands With Xcel
Google signed an agreement with Xcel Energy to supply clean energy for a new data center in Minnesota, continuing its strategy of matching expanding AI load with dedicated renewable procurement.
The deal adds to Google’s growing portfolio of long-term clean energy contracts and reinforces a pattern: hyperscalers are not waiting for generic grid capacity — they are contracting generation directly.
Why It Matters - Corporate procurement is shaping generation portfolios in real time. Utilities are planning around signed agreements, not hypothetical demand curves.
Grid Take - When large buyers lock in long-term supply, they de-risk projects and accelerate build decisions. The grid increasingly grows around named customers.
Upgrade to Grid Brief Premium to get extra deep dives into energy issues all over the world.
The Conversation
Quick Signals
The AI load debate has officially entered federal political management.
DOE is deploying balance sheet power to accelerate supply.
Capacity markets are flashing tight conditions across multiple regions.
Grid hardware — not ideology — is becoming the bottleneck.
Hyperscalers are anchoring supply through long-term contracts, not forecasts.
Things to Read
Energy Storage News on why data centers may be convenient scapegoats for broader grid failures — a pushback on load-blame narratives.
Renewable Energy World on lessons from Winter Storm Fern … outage management, resilience gaps, and planning blind spots.
OilPrice on the looming nuclear fuel supply gap that could constrain a U.S. nuclear expansion.
RealClearEnergy arguing that “unloved” coal remains essential during tight reliability conditions.