The grid is running into the machinery of its own reforms. PJM needs new firm capacity. Developers need turbines. Turbine queues are backed up. Interconnection rules were tightened to stop speculative projects. Now one serious gas project says those same rules could delay more than a gigawatt of dispatchable capacity.
That is the recurring theme this week. The country needs more power and faster grid access, but every solution runs into a process built for slower load growth. Columbia’s energy policy team says low-cost tools like GETs and demand response can cut pressure before customers get hit. Texas wants a 765-kV backbone for Permian load growth, while landowners argue they were not properly notified. FERC is forcing RTOs to rewrite large-load rules. DOE is offering $17.5 billion to revive large reactor construction. Everyone agrees speed is needed. The fights are over who gets charged, who gets delayed, and who gets to say no.
The Lede
GAS POWER
PJM Opposes Waiver for $2B Ohio Gas Plant

PJM told FERC it opposes a waiver request from Advanced Power Services that would let the company keep its Chestnut Run gas project in PJM’s fast-track Reliability Resource Initiative review. The project, located in Carroll County, Ohio, is a roughly $2 billion gas-fired plant owned by ArcLight-backed Advanced Power. The RRI process was built for shovel-ready projects and initially drew 51 projects totaling about 11.8 GW.
Advanced Power entered the RRI process using GE Vernova’s HA.03 turbine model and said the plant could be online by May 2030. Turbine backlogs have pushed that model out by at least two years. The company now wants to use GE Vernova’s HA.02 model, which would reduce the plant’s maximum output by about 550 MW while keeping the project close to its original schedule. PJM says the requested changes violate RRI rules that barred changes to project size and Capacity Interconnection Rights. Advanced Power says denial could delay more than 1.2 GW of firm, dispatchable capacity by about two years.
GridBrief Take: PJM is defending the integrity of a fast-track process created to stop queue games, and that concern is legitimate. The problem is that turbine scarcity is now colliding with resource adequacy. A waiver should come with strict conditions, updated milestones, and no special treatment on cost allocation. PJM also needs a process that can distinguish a real supply-chain adjustment from a developer trying to rewrite its bid after seeing the market.
Other Things to Check Out
AMAC: How America Should Respond to China’s Industrial Dominance Playbook
Drew Bond on how China uses subsidies, scale, and supply-chain control to dominate strategic industries.Reason: America’s Nuclear Industry Doesn’t Need Cronyism to Thrive
A pro-nuclear, anti-cronyism case for licensing reform and competition over federal favoritism.Reuters: Sodium Batteries Enter the AI Energy Race
Sodium-ion storage gets a closer look as data centers push demand for cheaper, less lithium-dependent batteries.MPR: Minnesota Studies New Nuclear
Minnesota lawmakers agreed to study new nuclear after decades under a construction moratorium.Bloomberg: Spain’s Renewables Boom Hits Investor Returns
Spain’s renewables buildout shows the financial risk when generation grows faster than transmission, storage, and flexible demand.
REPORT
Columbia: Use GETs and Demand Response Before Building the Expensive Stuff
Columbia University’s Center on Global Energy Policy released a commentary on electricity affordability and load growth that puts data centers inside the larger rate problem. The researchers identify several cost drivers: inefficient infrastructure planning, utility incentives that reward capital spending, underused flexibility, slow permitting, storm costs, wildfire costs, and supply chain inflation. Load growth from data centers compounds those pressures.
The report highlights near-term tools that already exist. Dynamic line ratings, advanced conductors, power flow controls, and other grid-enhancing technologies can increase capacity on existing infrastructure. Demand response can reduce peak demand, especially if large loads shape usage during constrained hours. Columbia also points to structural reform: better cost allocation for data centers, faster interconnection, permitting that connects price signals to actual supply, and utility regulation that rewards system optimization rather than only capital deployment.
GridBrief Take: Before regulators approve another giant capital plan, they should force utilities to show what dynamic ratings, reconductoring, demand response, and flexible large-load service can do first.
TRANSMISSION
Texas Landowners Push Back on 765-kV Buildout

Several hundred Central Texas property owners asked the Public Utility Commission of Texas to pause review of the proposed Bell County East to Big Hill 765-kV transmission line. The line is part of Texas’ high-voltage buildout to support projected load growth in the Permian Basin and broader ERCOT needs. Landowners say utilities failed to properly notify affected property owners after route changes.
The filing says more than 1,300 directly affected property owners were denied a chance to attend public meetings before their land was included in the project footprint. Oncor says it began public meetings in summer 2025, modified routes based on feedback, and responded to thousands of public comments. PUCT staff recommended 765-kV lines based on a 2024 ERCOT study because they can move more power over longer distances with fewer losses. Hearings were held June 8-12. A final PUCT decision is expected in September.
REGULATION
FERC Opens the Large-Load Rule Fight
FERC issued show-cause orders to CAISO, ISO New England, MISO, NYISO, PJM, and SPP after finding their large-load interconnection rules may be inadequate. The orders direct grid operators to address five areas: efficient study processes, cost-shift prevention, transparency into upgrade costs, co-location and behind-the-meter generation, flexible load services, and study processes for generation serving nearby large loads.
The commission chose regional proceedings rather than one national rule. That gives each RTO room to deal with its own grid conditions, but it also creates six separate timelines and six separate answers for developers. FERC’s orders also ask grid operators to evaluate alternative transmission technologies such as dynamic line ratings, advanced conductors, power flow devices, and synchronous condensers before defaulting to traditional network upgrades. RTOs and ISOs have 60 days to respond, with a possible extension process.
NUCLEAR
DOE Offers $17.5B for Large Nuclear Components

The Trump administration announced up to $17.5 billion in conditional loans to help utilities and energy companies purchase long-lead components for up to 10 Westinghouse AP1000 reactors. The loans would support up to five projects, each with two 1.1-GW reactors. The goal is to begin construction by 2030 and reduce timelines by ordering parts such as reactor vessels and steam generators in bulk.
The AP1000 is the only large advanced reactor design operating commercially in the United States. Vogtle Units 3 and 4 came online in Georgia in 2023 and 2024, but the project took about 15 years and cost around $35 billion, roughly double initial estimates. The DOE plan would require Westinghouse and utility partners to commit $500 million each per project before accessing federal funds. Seven utilities have expressed interest, according to Energy Secretary Chris Wright, though DOE has not named them.
GridBrief Take: Large nuclear will not return in the United States without solving the first-project risk problem. Bulk ordering can help rebuild the supply chain, but taxpayers should not become a permanent overrun account for one favored vendor. The cleanest nuclear policy is faster licensing, standardized designs, private offtake, credible cost-sharing, and no assumption that Washington can outguess construction risk better than balance sheets can price it.
Upgrade to Grid Brief Premium to get extra deep dives into energy issues all over the world.
Quick Signals
Reuters says data centers expose old power-policy failures. Douglas Arent argues that data centers are being blamed for a rate problem rooted in utility incentives, slow infrastructure, and poor cost allocation. His Columbia-linked argument tracks several recent GridBrief themes: demand growth can lower average costs when the system is built well, and it raises bills when planning and tariffs are bad.
Sodium-ion batteries get a data center push. Reuters reports that automakers and storage suppliers are accelerating sodium-ion battery production as data centers and grids demand more storage. GM is working with Peak Energy on Michigan production by 2028. Sodium-ion is still early, but lower material cost, wider temperature tolerance, and less cooling could make it useful for stationary storage.
ICF sees 445 GW of new capacity by 2030. A new ICF report says the U.S. could add 445 GW of capacity by 2030, mostly solar and storage. The report also says effective capacity is much lower than nameplate and that high-growth regions like Texas and PJM have little spare margin after 2027. The headline number is large. The reliability number is smaller.
Data centers are ready to trade flexibility for speed. Utility Dive reports that large-load customers are increasingly willing to negotiate curtailment, modular design, backup power, and flexible service if it helps them connect faster. That is where the large-load market is heading: firm service for customers willing to wait, conditional service for customers willing to move.
DOE coal orders now raise cost-allocation fights. E&E reports that a utility is pressing DOE over the cost of keeping a coal unit online under emergency authority. This was inevitable. Keeping plants open by federal order may help reliability, but someone still has to decide who pays for fuel, staffing, maintenance, and opportunity costs.
Newcleo advances its Italian test facility. NucNet reports that Newcleo installed the main vessel for a non-nuclear precursor test facility in Italy. The project supports the company’s lead-cooled fast reactor program. It is still a test facility, but advanced nuclear progress increasingly comes through supply-chain and demonstration steps before any reactor order.
European heat brings power-system stress back into view. Reuters’ heatwave tracker points to price spikes, power flows, cooling limits, grid alerts, and import dependence as the numbers to watch. Europe’s summer reliability problem is no longer just peak demand. It is also how weather affects generation, transmission flows, and thermal plant operation at the same time.
We rely on word of mouth to grow. If you're enjoying this, don't forget to forward Grid Brief to your friends and ask them to subscribe!

