  • Tariff Reprieve // PJM’s Data Center Squeeze // Transformer Crisis

Tariff Reprieve // PJM’s Data Center Squeeze // Transformer Crisis

A short-term trade truce keeps imports flowing, PJM scrambles to handle hyperscale load growth, DOE greenlights nuclear pilots—and transformer shortages threaten to stall the grid.

The U.S. grid’s stress fractures are showing. Tariff reprieves keep critical imports moving—at least for now—while PJM scrambles to handle the data center surge and DOE hands nuclear startups a fast pass to deployment. But behind it all, a quieter crisis is building in the transformer market, where manufacturing bottlenecks and policy choices threaten to choke the entire buildout of generation and transmission capacity.

Transformer Troubles: Supply Chain Bottlenecks Threaten Grid Buildout

A perfect storm of surging demand, aging infrastructure, raw material tariffs, and a thin domestic manufacturing base has pushed U.S. power transformers into chronic shortage. Without relief, utilities could face multi-year project delays, higher costs, and greater vulnerability during extreme weather.

Key Points:

  • Demand spike: Electricity use up 7% since 2020—driven by data centers, manufacturing expansion, and electrification—has doubled or tripled demand for certain transformer classes since 2019.

  • Aging fleet: Over half of the nation’s 40 million distribution transformers are past their 33-year service life.

  • Import dependence: 80% of power transformers and 50% of distribution units now come from abroad; GOES steel and copper tariffs are set to push prices higher.

  • Capacity crunch: Lead times have ballooned and costs are up as much as 95% for some distribution units; OEMs cite skilled labor shortages and lack of standardization as key barriers to scaling.

  • Investment gap: $1.8B in announced capacity expansions isn’t enough to close the 30% deficit in power transformers; policy uncertainty is keeping manufacturers from betting bigger.

Tariffs Extended, Transmission Tension

The White House’s 90-day extension on paused China tariffs keeps U.S. imports of transformers, solar panels, batteries, and high-voltage components flowing at the current reduced rate until November. For grid planners, it buys breathing room: much of America’s substation and inverter hardware still comes from Chinese factories, despite years of “friend-shoring” talk. A sudden tariff snapback could have added 20–30% to project costs mid-bid, stalling transmission upgrades and storage deployments. But the reprieve is temporary—developers have a short window to lock in orders before another round of trade brinkmanship.

PJM Rushes to Rein in Data Center Surge

PJM is racing to finalize interconnection and capacity rules for hyperscale loads like data centers, targeting FERC approval before summer 2029 capacity auctions. The move comes as the region’s peak load forecast soars 32 GW by 2030—almost entirely from data centers—and supply already runs tight. Reliability pressure is mounting: the last two capacity auctions set record prices, driven by thin reserve margins and sluggish new buildouts. PJM is weighing blunt tools like load caps for non-capacity-backed customers and forcing big users to bring their own generation—a path that could normalize privately financed peaker plants inside corporate campuses.

DOE Names First 11 Reactor Pilots

The Department of Energy has tapped 11 companies to fast-track advanced reactor tests under Trump’s new Nuclear Reactor Pilot Program, with a goal of at least three achieving criticality by July 4, 2026. These aren’t just lab curiosities—projects from Oklo, Last Energy, and Terrestrial Energy could leapfrog years of NRC red tape and move straight toward commercial deployment. If the pilots hit timelines, modular reactors could start appearing in mining operations, military bases, and remote industrial hubs before 2030—providing firm power without long transmission buildouts. That’s a potential paradigm shift in how new load centers get supplied.

And the winners are…

  • Aalo Atomics Inc.

  • Antares Nuclear Inc.

  • Atomic Alchemy Inc.

  • Deep Fission Inc.

  • Last Energy Inc.

  • Oklo Inc. (two projects)

  • Natura Resources LLC

  • Radiant Industries Inc.

  • Terrestrial Energy Inc.

  • Valar Atomics Inc.

Upgrade to Grid Brief Premium to get extra deep dives into energy issues all over the world.

Conversation Starters

  • FortuneAI Experts Return From China Stunned: U.S. Grid So Weak, the Race May Already Be Over – China’s decades-long overbuild has left it with twice the capacity it needs, letting it soak up AI demand; U.S. grids run on razor-thin margins, forcing load-shedding debates before the boom even peaks.

  • Tom’s HardwareAI’s Insatiable Power Demand Is Outpacing Grid Development – U.S. companies are building private power plants to bypass local grid constraints, signaling a splintering of centralized electricity planning in favor of corporate microgrids.

  • Science AlertFrance’s Largest Nuclear Plant Halted by Jellyfish – A swarm clogged cooling pumps at Gravelines, idling four reactors; it’s a reminder that even baseload nuclear isn’t immune to nature-induced outages.

Good Bet, Bad Bet

Good Bet: Oklo (OKLO) – With two projects selected for DOE’s pilot, Oklo now sits at the center of the fastest-moving regulatory pathway for U.S. nuclear in decades. If it delivers even one criticality on schedule, it could own the early market for microreactors serving off-grid and industrial customers.

Bad Bet: Equinix (EQIX) – As PJM and other ISOs weigh rules to cap or surcharge non-capacity-backed loads, colocation-heavy operators like Equinix face higher interconnection costs and slower approval timelines—both poison to hyperscale expansion economics.

Share Grid Brief

We rely on word of mouth to grow. If you're enjoying this, don't forget to forward Grid Brief to your friends and ask them to subscribe!